How much does a condo remodel cost in Boca Raton?+
Ranges from recent Boca market data and our own condo invoicing. Single-room refreshes and pre-sale cosmetic work typically run $50K–$150K. Multi-room remodels and standard full-unit work (kitchen + 1–2 baths + flooring + paint + lighting) usually fall in the $150K–$400K range. Luxury oceanfront and intracoastal full-unit gut remodels with imported finishes, natural stone throughout, and custom millwork run $400K–$1.5M+. Boca condo remodels typically cost 20–40% more per square foot than comparable single-family remodels the logistics premium (elevator windows, work-hour limits, COI churn, board inspections, engineer letters) is real and gets priced into every trade.
How long does a condo remodel take, start to finish?+
Plan for 4–8 months from signed project agreement to final inspection for most Boca condo projects. Breakdown: board alteration-agreement package assembled and submitted 2–3 weeks; board review 2–6 weeks from complete submittal (incomplete packets add 2–4 weeks per revision); City of Boca Raton permits 5–7 weeks on a separate track after board approval; on-site build 8–20 weeks depending on scope and the building's work-hour window. Condo schedules are compressed by work-hour limits a 10-week single-family project commonly runs 14–16 weeks in an oceanfront tower with 10am–3pm loud-work windows.
Do I need board approval, and what goes into the package?+
For any work beyond strict cosmetic, yes. Under Florida law and every Boca condo's declaration, alteration of a unit requires an alteration agreement signed by both owner and association before work begins. A complete package typically includes: alteration agreement signed by owner and board; Certificate of Insurance naming association and management company as additional insureds; copy of our state general contractor license (CGC1514129); project summary with scope drawings and materials list; written timeline; refundable damage deposit or performance bond (varies by building). For projects touching plumbing stacks, electrical panels, or load-bearing elements, boards often require an engineer letter. We assemble every piece you sign and attend the board meeting if required.
Does my contractor need to give my building a COI, and what goes on it?+
Yes every Boca condo building requires a Certificate of Insurance before any work, and most require it posted with the concierge or management before the contractor's first elevator reservation. A proper COI names the association, the management company, and usually the board as additional insureds under CG 20 10 (ongoing operations) and CG 20 37 (completed operations) endorsements, and typically requires a waiver of subrogation. General-liability limits and umbrella requirements vary by building. Workers comp is required for any contractor with employees; subcontractors provide proof or a Florida Certificate of Election to be Exempt. We handle the COI paperwork with your management company directly.
What are the sound-transmission rules, and can I install hardwood?+
The Florida Building Code requires IIC = 50 lab or = 45 field, and STC = 50 lab or = 45 field between dwelling units. IIC measures footstep and impact noise; STC measures airborne voice and TV. A bare concrete slab rates only IIC 28–35 below code so any hard-surface flooring requires an acoustic underlayment. A 6mm cork underlayment adds 15–22 IIC points; engineered acoustic mats (QuietWalk, Pro-Flex) add 18–28 points. Many Boca boards layer their own rules on top a common one is the "80/20 rule" or "15% rule" limiting hard-surface flooring to a percentage of unit area or requiring soft-covered flooring in bedrooms. We spec the underlayment and floor assembly to pass both code and board rule, and schedule a field IIC test (ASTM E1007) before closeout when a board requires one.
Can I move my kitchen or bathroom?+
Usually no and this is the biggest constraint most new condo owners discover after committing to a remodel. Your kitchen and bathroom are located where the vertical plumbing stacks land; that stack serves every unit above and below your column. Relocating it risks leaks, loss of pressure, code violations, and litigation from neighbors in your column. Within the existing footprint you have significant freedom reconfigure cabinet layout, move appliances within a few feet, change sink location within the vanity or counter run. Moving the kitchen to the living room or a bath across the unit is almost never feasible in a standard Boca high-rise and requires formal engineering review plus board approval even when it is.
What are the work-hour, elevator, and logistics rules in a Boca condo?+
The City of Boca Raton's noise ordinance prohibits construction noise above residential limits before 7am or after 6pm Monday–Friday, before 8am or after 6pm Saturday, and any time on Sunday. Condo boards typically narrow this further common building windows are 9am–4pm or 9am–5pm Monday–Friday, with loud work (demo, tile cutting, jackhammer) often restricted to 10am–3pm. Weekends and holidays are almost always prohibited in occupied towers. Freight elevators typically require 48–72 hour advance reservation in 4-hour blocks, with a refundable damage deposit (commonly $250–$1,000). We build your building's specific rules into the written schedule at project agreement signing.
Can I live in the unit during a condo remodel?+
For a single-room refresh or a kitchen-only project in a large unit, yes we seal the work zone with plastic barriers + negative-pressure fan, keep one full bath and a temporary kitchen functional, and maintain a clean sleeping zone. For a full-unit gut, almost every client relocates there's no way to isolate a dust-free, sound-reasonable sleeping space when every wet area is offline and demo runs in the work-hour window. Many Boca condo clients are seasonal residents who plan the project during months they're not in residence, which also sidesteps the noise and access questions entirely.
What happens to an active project if a hurricane is forecast?+
We run a written pre-hurricane closeout protocol. Once the National Hurricane Center issues a watch or warning including Palm Beach County, we: remove all loose material from balconies and common areas (projectile risk); install pre-fit panels over any opened glazing; turn off unit water at our isolation valve; remove tools and loose material from freight elevators and loading docks (building typically requires this 72 hours before projected landfall); walk the unit with the building engineer if required; stage materials off-site until the association reopens access post-storm. Post-storm re-entry is coordinated by management we don't re-enter until the association formally reopens. Any in-progress weather damage is documented for your HO-6 claim within 24 hours of re-entry. Protocol is in every condo project we undertake.
Do I need a City of Boca Raton permit for a condo remodel?+
Yes, for almost every real condo remodel not just the board's approval. Under the Florida Building Code and the City of Boca Raton building ordinance, a permit is required any time you alter plumbing, electrical, mechanical, or structural systems, and every real condo remodel touches at least one. Strictly cosmetic work (paint, replacing a vanity into identical plumbing, swapping a toilet in place) is exempt. City permits run on their own track separate from board approval we pull every required permit in our name as the licensed GC (CGC1514129), schedule inspections, and deliver every permit and inspection report in your closeout binder. Board approval is the first gate; City permit is the second.
How are payments structured, and does board approval affect payment timing?+
Condo remodels are drawn as milestone draws tied to written completion gates not time-based invoices. Typical schedule: 10% earnest at project agreement signing; 10–20% at board approval + COI posted (applied to permits, design, and long-lead material orders, compliant with Florida Statutes 489.126 limits); then draws at demo complete, rough-trades inspected, drywall complete, cabinets + stone set, and final with punch and closeout. Each draw invoices against verifiable progress with lien waivers from every paid subcontractor. Some buildings require a board-observed inspection at demo and at pre-tile waterproofing we build those into the schedule as formal milestones.